Installation began after the construction of the building ready, ie when all the holes, Stroebe, niches in walls and ceilings, is a mark of pure sex, the walls are plastered areas over which the pipe will be opened, dug a trench for the issuance and completed all work associated with the use of open fire.
Installation of the system starting with the release, then collect the riser from the bottom up, then, from frogs sprue, assemble floor outlets. Sheaths elements directed towards the flowing stream. Strictly observe the slopes.
A large thermal elongation of plastics makes taking care that the PEX pipe do not bend when used. Therefore, when assembling Spigot joints with a rubber gasket between the face of a smooth end of the tube and the base dressed in her funnel leave a gap of 10 mm. He is able to compensate for the thermal elongation of the tubing length to 2 m.